Reconstruction and strengthening of critical infrastructure

The objective of this component is to support the reconstruction/restoration of damaged public buildings, such as hospitals, schools, higher and technical education buildings, fire stations, and selected block and district offices, and other important public buildings. It will include the restoration of partially damaged structures and the reconstruction of fully damaged structures, including equipment and furniture.
The component will finance infrastructure and equipment damaged by the disaster, and improvements to current structures to increase resilience. Assessments will be carried out to determine the extent of structural integrity and retrofitting/reconstruction needs. For hospitals, the reconstruction will be focused on replacement of damaged specialized medical equipment, setting up specialized equipment on higher levels which will entail strengthening the structural integrity of buildings in order to be able to sustain the heavy load. For some hospitals, special diagnostics and pathology sections/extensions will be built since existing structures will be unable to sustain the load of heavy equipment on higher levels. Some older hospitals will also require retrofitting in order to ensure seismic resistance. The component will also finance the repair and reconstruction of damaged higher education and technical buildings, fire station, and other public buildings, including the procurement of equipment/furniture, etc.

 

Component 1 - Construction and strengthening of critical infrastructure (USD 60 Mn, INR 360 Crores)

S. NoName of the workExecuting agencyEstimated cost in INR CroreExpdtt. incurred in CroreStatus/ issues
1Construction of Humanities block and staff rooms cum meeting hall block at GDC BeminaR&B-Kashmir9.00Earthwork completed in one block. GSB filling and mud mat completed..Work yet to be resumed after Lockdown.
2Construction of Administrative Block at GDC for Women AanantnagR&B-Kashmir2.28Contract Agreement signed on 17-12-2019. Work yet to be started.
3Construction of additional classroom block at GDC BijbaheraR&B-Kashmir9.22Foundation raft completed. Column reinforcement raised. Plinth beam in progress.
4Construction of Science Block at Amar Singh College SrinagarR&B-Kashmir7.19Eathwork excavation for foundation completed.GSB filling and mud mat completed
5Construction of classroom block of GDC women M.A road SrinagarR&B-Kashmir13.34For foundation 10 piles stand cast. Load testing for second working pile accomplished and work in progress.
6Construction of 120 bedded new IPD/OT block with spinal care centre at Bone and Joint Hospital SrinagarR&B-Kashmir88.94Contract Signed on 24-06-2019.Dismantling of existing structures completed. Disposal of dismantled material completed.
7Construction of Lal Ded Hospital in SrinagarJKPCC132.50Piling work in progress.
8Construction of 01 Fire Station building in Kashmir at BatmalooR&B-Kashmir9.067Agreement signed on 02-06-2020
9Construction of HSS Jawahar Nagar, Srinagar.(Through JKPCC).JKPCC5.272nd floor slab laid. Also Brick work for 2nd floor completed
10Construction of 02 class rooms at M S Shivpora and 02 class rooms at Batwara SrinagarR&B-Kashmir1.55Work started with soil investigation ,barricading, toilet facilities but drawings are awaited due variation in quantities/ SBC issue.
11Contstruction of 04 class rooms at HSS samoora, 04 class rooms at HS Dogripoa, 02 class rooms at GMS Rakhi Littar, 02 classs rooms at GMS Batpora Naina, 02 class rooms at GPS afganipora of Dist Pulwama.R&B- Kashmir4.50Construction of single storey completed. Finishing work under completion at HSS Samoora,Construction of single storey completed. Finishing work under completion at HS Dogripora,construction of single storey completed. Finishing work under completion at GMS Raki Littar,Slab Laid at Batpora Naina,Geo technical ionvestigation repeated. Drawings have not been issued to Contractor at afganipora.
12Consttruction of 2 classrooms at GBHS Nazneenpora,Consttruction of 2 classrooms at GUPS Melhura,Consttruction of 2 classrooms at GUPS Reban of Dist. ShopianR&B- Kashmir2.44Agreement Signed on 16.04.2019. Work initiated at Nazneenpora,B.C issue resolved and Revised drawings issued at Melhora,Work completed up to plinth Level at Reban Shopian.
13Construction of 2 classrooms in GMS Batipora Naidkahi ,Construction of 2 classrooms GBHSS Nowgam , Construction of 4 classrooms in GMS Bakepora, Baniyari of Dist Bandipora.R&B- Kashmir3.46to be retendered.
14Construction of 4 classroomsin GBHS verinag,Construction of 4 classrooms GHSS Hakura of Dist. Anantnag.R&B-Kashmir2.485to be retenderd.
15Const. of 4 classrooms in GMS Gund-i-kilam, Kulgam.R&B-Kashmir1.06Letter to proceed issued on 26-12-2019 . Work yet to be started.
16Const. of 4 classrooms in GMS Kulhama.Bandipora.R&B-Kashmir1.148Letter to proceed issued on 04-02-2020.Work not started yet.
17Construction of 2 classrooms in GMS Naikpora,Construction of 4 classrooms,GGHSS Yaripora of Dist. Kulgam.R&B-Kashmir2.0The building is raised upto columns.Shuttering of Slab in progress at Naikpora,Work not started due to non availability GFC at Yaripora.
18 Construction of 02 class room in GMS Arwani, Construction of 4 class room in GHSS Arwani,Construction of 2 classrooms in GMS Hafizabad,Construction of 2 classrooms in GMS Subhanpora, Construction of 4 classrooms in GBMS Tawella of Dist. Anantnag.R&B-Kashmir4.544Footing completed and columns raised. Work resumed at GMS Arwani, Laying of Plinth Beam in progress. Work resumed at GHSS Arwani,Laying of Plinth Beam in progress. Work resumed at Hafizabad,Foundation completed upto plith level. Work resumed at Subhanpora,Work yet to start., drawings not issued as per new geo technical investigation at Tawella.
19Construction of 2 class rooms in GHS Narbal, Construction off 4 Class rooms in GGHSS Magam,Construction of 4 classrooms in GHS SaiL of Dist. Budgam.R&B- Kashmir2.61Awarded on 16-08-2019.Work not started yet due to site dispute.
20Construction of 2 classrooms in GHS Jablipora ,Construction of 2 classrooms in GHSS Wanpoh, Construction of 2 classrooms in GMS Ketriteng, Construction of 4 classrooms in GBHSS Bijbehara ,Construction of 4 classrooms in GGHSS, Bijbehara of Dist. Anantnag.R&B - Kashmir4.20Work in progress after issuing drawings in Feb,2020. Work not resumed at Jablipora, Agreement signed on 11.04.2019. Work yet to be started due to non availability of drawings after resolving B.C.issue at Wanpoh, Agreement signed on 11.04.2019. Work started on foundation and is in progress at Katriteng, Shuttering of slab in progress at Bijbehara, Completed upto Slab level at GGSS Bijbehara.
21Construction of2 classrooms,in GPS QaziporaTangmarg, Construction of 4 classrooms in GGHSS Lalpora Kunzer of Dist. BaramullaR&B - Kashmir1.775Agreement signed on 17-10-2019. Work not started yet.
22Construction of 2 classrooms, Galibal, Baramulla.R&B Kashmir0.926Bids Opened, under financial evaluation.However cleared by TAQAC/PMU.
23School Package-01 (R&B Div-II ,Jammu) GMS Chibba,School Package-01 (R&B Div-II ,Jammu) GMS DhoonR&B -Jammu0.840LOA issued on 21/12/2019.ESSR GMS Dhoon cleared - ESSR for GMS Chibba pending due to court case by land encroacher. Hence Agreement yet to be signed.
24School Package-02-1 (R&B Div-III ,Jammu) GMS MakawalR&B -Jammu0.386LOA Cancelled for approval submitted to WB.To be retendered.
25School Package-02-2: (R&B Div-III ,Jammu) GPS Gujjar basti( Kamaillaychak)R&B -Jammu0.850LOA Cancelled for approval submitted to WB.To be retendered.
26School Package-02-3:(R&B Div-III ,Jammu), GMS PargwalR&B -Jammu0.479Agreement signed on 22.05.2020 . Structural designing in progress.
27School Package-03-1:(R&B Div-I ,Jammu), GGPS BelicharanaR&B -Jammu0.380LOA issued 14/11/2019 -Agreement Signed on 02 -12 -2019. Soil Investigation & Structural Design completed. Excavation for foundation in progress.
28School Package-03-02:(R&B Div-I ,Jammu), GHS Chak- majraR&B -Jammu0.474LOA issued 09/10/2019 -Agreement Signed on 07-03-2020. ESSR cleared. Structural designing in progress.
29School Package-03-03:(R&B Div-I ,Jammu), GMS PuranapindR&B -Jammu0.733LOA issued 09/10/2019 -Agreement tSigned on 07-03-2020- ESSR cleared. Structural designing in progress.
30School Package- 04: (R&B Div-Basohli) H SS Nagrota Gujru, GHS Gurah KalyalR&B- Jammu1.453LOA issued 23/12/2019. Agreement Signed on 04.02.2020. Soil Investigation / Structural design completed. Work yet to start.
31School Package-05-1: (R&B Div-Udhampur) GHS S K BerR&B- Jammu0.709LOA issued on 31/12/2019 - Conditional ESSR clearance accorded. Agreement to be Signed.
32School Package-05-2: (R&B Div- Udhampur), GMS UppermantaR&B- Jammu1.181LOA issued on 31/12/2019 . ESSR cleared by the World Bank.Agreement signed on 27.05.2020. Work yet to start.
33School Package- 05-3: (R&B Div- Udhampur), GMS Berrian ManyalR&B- Jammu0.836Non-responsive. To be re-tendered. For approval sent to WB.
34School Package 06-1: (R&B Div- Nowshera) GMS PratR&B- Jammu0.540Under Financial Evaluation. ESSR cleared by the WB.
35School Package 06-2: (R&B Div- Nowshera), GMS ThickhaR&B -Jammu0.540Under Financial Evaluation. ESSR cleared by the WB.
36School Package-06-3:(R&B Div- Nowshera), GPS RajgarahR&B -Jammu0.525LOA issued 31/12/2019. Agreement Signed on 20.04.2020. ESSR clreared by the World Bank. Work initiated.
37Package-08-1: (R& B Div - Rajouri) , GHS Gambhir MujhalanR&B -Jammu0.809LOA issued on 28/12/2019 -Agreement signed on 21.04.2020 - Conditional ESSR clearance accorded.
38Package-08-2:(R& B Div - Rajouri), GHSS RajouriR&B -Jammu1.360LOA issued on 31/12/2019. ESSR to be submitted.after land deed completion. Hence Agreement to be signed.
39Package-09-01:(R& B Div - Poonch) , GMS Biassan KayeinR&B -Jammu0.595LOA issued on 29-7-2019. Agreement signed on 12.09.2019. Soil Investigation / Structural Design in progress
40Package-09-02: (R& B Div - Poonch) , GMS nari (NB)R&B -Jammu1.148LOA issued on 29-7-2019. Agreement signed on 12.09.2019. Soil Investigation / Structural Design in progress.
41Package-09-03- (R& B Div - Poonch) , GMS QasbaR&B -Jammu1.468LOA issued on 16-01-2020 - Agreement signed on 03.03.2020. Conditional ESSR clearance accorded.
42Package-09-04: (R& B Div - Poonch) , GMS Kiranmorian -AraiR&B -Jammu0.876LOA issued on 16-01-2020 - Agreement signed on 03.03.2020. Conditional ESSR clearance accorded. Work not started yet.
43Package-10: (R& B Div - Poonch), GPS palani khanetarR&B -Jammu1.138LOA issued on 20-01-2020 - Agreement signed on 31.01.2020. Work yet to start.
44Package-11-1: (R& B Div -Poonch ,Sub Div-Mendhar) , GMS Dhara, J W galiR&B -Jammu0.833Non-responsive. To be re-tendered. Uploaded on STEP for approval of retendering.
45Package-11-2: (R& B Div -Poonch ,Sub Div-Mendhar) GPS JabranR&B -Jammu0.833Non-responsive. To be re-tendered.
46Package-11-3 (R& B Div -Poonch ,Sub Div-Mendhar), GMS KhaitR&B -Jammu0.801Non-responsive. To be re-tendered.