The objective of this component is to restore and improve the connectivity disrupted due to the disaster through the reconstruction of damaged roads and bridges. The infrastructure will be designed to withstand earthquake and flood forces as per the latest official design guidelines. The affected areas will benefit by the restored access to markets thereby increasing the economic growth in these areas and timely access to health and education services. Restoration of roads will also serve as supply/rescue lines in the event of a disaster.
The component will finance the reconstruction of damaged roads, bridges and associated drainage and slope stabilization works, retaining walls, breast walls and other structures to increase resilience.
Component 2 - Construction of Roads & Bridges (USD 80 Mn ; INR 480 Crores)
S. No Name of the work Executing Agency Estimated Cost in Crore INR Expdtt. Incurred Status/Issues 1 Widening up-gradation of Amberpora Haritar Akhoonpora road Baramulla 8.375 Work in progress - 31% (Physical Progress) 2 Construcion of Halmullah Punchpora Kralkut road Sangam Bijbehara district Anantnag 4.98 Work is in progress - 21 % (Physical Progress) 3 Construction of Littter Pulwama road 3.36 Work is in progress 23 % (Physical Progress) 4 Construction of Rohmoo Bridge 21.25 Work in progress- 42 % (physical progress) 5 Construction of Trenz Bridge 34.5 Work in progress - 30 % (Physical Progress) 6 Construction of 1x50 m span trussed Girder steel Girder bridge over Frastharnallah at Waza Mohalla Kreeri at Baramulla 7.4 Work in progress (Physical progress-32%). Land issue in approach roads and tree cutting 7 Construction of 1X50m trussed grider over Niglinallah at Shrakhwara on Putkhah Wagoora Barmulla 6.7 Work in progress (Physical Progress 47%) -Land Issue in approach roads, canal issue and tree cuttings 8 Construction of 1x25.2 m span plate Girder steel lane bridge over nallah sheeshrie on wahdina bandi payeen Baramulla 5.32 Work in progress- 47% (physical progress) 9 Construction of 1x25.20 m RCC double lane bridge over nallah ferozpura Baramulla at trikolbal pattan Baramulla 6.31 Work in progress - 31% (Physical Progress) 10 Construction of 1x19.20 m plate girder double lane steel bridge over niglinallah at ghogidaji Baramulla 6.27 Physical Progress:46 %. Variation proposal submitted to WB on 19-11-2019. 11 Construction of 1x50 span trussed girder double lane steel bridge over ningli nallah a wagila wagoora Baramulla 8.66 Work in progress 35 % (Physical Progress) 12 Construction of steel truss girder bridge 3x 30 m at Asajipora Kamad Sadoora Road km 4th 6.31 Finlization of design in progress with PIU. Clearance conveyed by PMU as discussed in WB mission meeting (Feb 17-20). ESIA not submitted. 13 Kalaiban Bridge 2.63 Finalization of design with PIU. Clearance conveyed by PMU as discussed in WB mission meeting in Feb 2020 ESIA not submitted. 14 Construction of 2 lane single span 110 m bridge over nallah sindh at Wayil Ganderbal 23.79 Finalization of design with PIU. Clearance conveyed by PMU as discussed in WB mission meeting in Feb 2020. ESIA not submitted. 15 Construction of bridge of Kulgam Chamund road Km-Ist RD-700 32.4 Finalization of design with PIU. Clearance conveyed by PMU as discussed in WB mission meeting in Feb 2020. ESIA not submitted. 16 Construction of 1x45 Mtr trussed girder bridge over nallah Rambiara at Kumar Mohalla Watchi 3.11 Finalization of design with PIU. Clearance conveyed by PMU as discussed in WB mission meeting in Feb 2020. ESIA not submitted. 4th Tawi Bridge including construction of Protection works ( A1 & A2) 0 Dropped 17 43M span steel deck bridg over Anji Nallah at Sukhal Ghat,Reasi (complete job) 1,22 L.O.A issued on 30-07-2019. Contract Agreement signed on 13-03-2020. 18 Const. of 165 M (3x55m) span bridge double lane brigde over Betar nallah at village Dhallan 18 Agreement signed on 07-03-2020. 19 58 m span motorable bridge over Katheel Ganjoo to Barsoa over Ghordi nallah and 50 m span motorable bridge from Barso to Pathri over Barmeen nallah Ramnagar Udhampur 13.24 L.O.A issued on 30-07-2019. Signing of Contract Agreement underway.. 20 Construction of roads (Kadlabal Lasjan Rambagh Road)-Package-1 126 Bids recieved on 18-12-2019. Under Evaluation 21 Construction of roads (Pampore Pulwama Road)-Package-1 22 Construction of roads (Hamaray Sultanpora Nowgam to Sumbul Bridge, Shadipura Khanpeth Sumbal road, Hajin Ajas Via Saidnara )-Package-2 31.89 Awarded A sgreement to be signed. 23 Construction of roads (Rigid Pavement of IG Road Rambagh to Civil Secretariat in Srinagar districtPackage-3 42.52 Awarded on 08.01.2020. Agreement yet to be signed. 24 Construction of roads ( Rigid Pavement of Eastern Foreshore road, )-Package-3 25 Construction of roads (Rigid Pavement of IG Road Peerbagh Bridge to Humhama Chowk in Srinagar)-Package-3 26 Construction of roads ( Parimpora Soibugh in Budgam)-Package-3 27 Construction of Roads (Sangam Khudwani Road, & Bijbehara waghama via katriteng Road. )-Package-4 Awarded. Agreement yet to be signed. 28 Construction of Roads ( Sidhra-Surinsar Road (Lot 1)
42.54 Awarded. Contract agreement signed on 13-03-2020. 29 2. Tutan Di Khui to Khada-Madana Road (Lot 2) Tendered on 09.06.2020. Bid submission dated 20.07.2020 30 Construction of Roads (Chiralla Link Road and
2. Malaini-Chakrabatti Road)-Package-2 35 Tendered on 04.06.2020. Bid submission dated 14.07.2020 31 Construction of Roads (Malaini-Chakrabatti Road)-Package-2 32 Construction of Roads (Gulati to Shadra Sharief)-Package-3 38.97 LOA issued on 23-12-2019. agreement signed on 13-3-2020. 33 Construction of Roads (Anji Panasa Road , Deva Mai Ohli Mandir)-Package-4 16.04 Awarded. Agreement signed on 13-03-2020.
S. No | Name of the work | Executing Agency | Estimated Cost in Crore INR | Expdtt. Incurred | Status/Issues |
---|---|---|---|---|---|
1 | Widening up-gradation of Amberpora Haritar Akhoonpora road Baramulla | 8.375 | Work in progress - 31% (Physical Progress) | ||
2 | Construcion of Halmullah Punchpora Kralkut road Sangam Bijbehara district Anantnag | 4.98 | Work is in progress - 21 % (Physical Progress) | ||
3 | Construction of Littter Pulwama road | 3.36 | Work is in progress 23 % (Physical Progress) | ||
4 | Construction of Rohmoo Bridge | 21.25 | Work in progress- 42 % (physical progress) | ||
5 | Construction of Trenz Bridge | 34.5 | Work in progress - 30 % (Physical Progress) | ||
6 | Construction of 1x50 m span trussed Girder steel Girder bridge over Frastharnallah at Waza Mohalla Kreeri at Baramulla | 7.4 | Work in progress (Physical progress-32%). Land issue in approach roads and tree cutting | ||
7 | Construction of 1X50m trussed grider over Niglinallah at Shrakhwara on Putkhah Wagoora Barmulla | 6.7 | Work in progress (Physical Progress 47%) -Land Issue in approach roads, canal issue and tree cuttings | ||
8 | Construction of 1x25.2 m span plate Girder steel lane bridge over nallah sheeshrie on wahdina bandi payeen Baramulla | 5.32 | Work in progress- 47% (physical progress) | ||
9 | Construction of 1x25.20 m RCC double lane bridge over nallah ferozpura Baramulla at trikolbal pattan Baramulla | 6.31 | Work in progress - 31% (Physical Progress) | ||
10 | Construction of 1x19.20 m plate girder double lane steel bridge over niglinallah at ghogidaji Baramulla | 6.27 | Physical Progress:46 %. Variation proposal submitted to WB on 19-11-2019. | ||
11 | Construction of 1x50 span trussed girder double lane steel bridge over ningli nallah a wagila wagoora Baramulla | 8.66 | Work in progress 35 % (Physical Progress) | ||
12 | Construction of steel truss girder bridge 3x 30 m at Asajipora Kamad Sadoora Road km 4th | 6.31 | Finlization of design in progress with PIU. Clearance conveyed by PMU as discussed in WB mission meeting (Feb 17-20). ESIA not submitted. | ||
13 | Kalaiban Bridge | 2.63 | Finalization of design with PIU. Clearance conveyed by PMU as discussed in WB mission meeting in Feb 2020 ESIA not submitted. | ||
14 | Construction of 2 lane single span 110 m bridge over nallah sindh at Wayil Ganderbal | 23.79 | Finalization of design with PIU. Clearance conveyed by PMU as discussed in WB mission meeting in Feb 2020. ESIA not submitted. | ||
15 | Construction of bridge of Kulgam Chamund road Km-Ist RD-700 | 32.4 | Finalization of design with PIU. Clearance conveyed by PMU as discussed in WB mission meeting in Feb 2020. ESIA not submitted. | ||
16 | Construction of 1x45 Mtr trussed girder bridge over nallah Rambiara at Kumar Mohalla Watchi | 3.11 | Finalization of design with PIU. Clearance conveyed by PMU as discussed in WB mission meeting in Feb 2020. ESIA not submitted. | ||
4th Tawi Bridge including construction of Protection works ( A1 & A2) | 0 | Dropped | |||
17 | 43M span steel deck bridg over Anji Nallah at Sukhal Ghat,Reasi (complete job) | 1,22 | L.O.A issued on 30-07-2019. Contract Agreement signed on 13-03-2020. | ||
18 | Const. of 165 M (3x55m) span bridge double lane brigde over Betar nallah at village Dhallan | 18 | Agreement signed on 07-03-2020. | ||
19 | 58 m span motorable bridge over Katheel Ganjoo to Barsoa over Ghordi nallah and 50 m span motorable bridge from Barso to Pathri over Barmeen nallah Ramnagar Udhampur | 13.24 | L.O.A issued on 30-07-2019. Signing of Contract Agreement underway.. | ||
20 | Construction of roads (Kadlabal Lasjan Rambagh Road)-Package-1 | 126 | Bids recieved on 18-12-2019. Under Evaluation | ||
21 | Construction of roads (Pampore Pulwama Road)-Package-1 | ||||
22 | Construction of roads (Hamaray Sultanpora Nowgam to Sumbul Bridge, Shadipura Khanpeth Sumbal road, Hajin Ajas Via Saidnara )-Package-2 | 31.89 | Awarded A sgreement to be signed. | ||
23 | Construction of roads (Rigid Pavement of IG Road Rambagh to Civil Secretariat in Srinagar districtPackage-3 | 42.52 | Awarded on 08.01.2020. Agreement yet to be signed. | ||
24 | Construction of roads ( Rigid Pavement of Eastern Foreshore road, )-Package-3 | ||||
25 | Construction of roads (Rigid Pavement of IG Road Peerbagh Bridge to Humhama Chowk in Srinagar)-Package-3 | ||||
26 | Construction of roads ( Parimpora Soibugh in Budgam)-Package-3 | ||||
27 | Construction of Roads (Sangam Khudwani Road, & Bijbehara waghama via katriteng Road. )-Package-4 | Awarded. Agreement yet to be signed. | |||
28 | Construction of Roads ( Sidhra-Surinsar Road (Lot 1) | 42.54 | Awarded. Contract agreement signed on 13-03-2020. | ||
29 | 2. Tutan Di Khui to Khada-Madana Road (Lot 2) | Tendered on 09.06.2020. Bid submission dated 20.07.2020 | |||
30 | Construction of Roads (Chiralla Link Road and 2. Malaini-Chakrabatti Road)-Package-2 | 35 | Tendered on 04.06.2020. Bid submission dated 14.07.2020 | ||
31 | Construction of Roads (Malaini-Chakrabatti Road)-Package-2 | ||||
32 | Construction of Roads (Gulati to Shadra Sharief)-Package-3 | 38.97 | LOA issued on 23-12-2019. agreement signed on 13-3-2020. | ||
33 | Construction of Roads (Anji Panasa Road , Deva Mai Ohli Mandir)-Package-4 | 16.04 | Awarded. Agreement signed on 13-03-2020. |