Reconstruction of roads and bridges

The objective of this component is to restore and improve the connectivity disrupted due to the disaster through the reconstruction of damaged roads and bridges. The infrastructure will be designed to withstand earthquake and flood forces as per the latest official design guidelines. The affected areas will benefit by the restored access to markets thereby increasing the economic growth in these areas and timely access to health and education services. Restoration of roads will also serve as supply/rescue lines in the event of a disaster.
The component will finance the reconstruction of damaged roads, bridges and associated drainage and slope stabilization works, retaining walls, breast walls and other structures to increase resilience.

 

Component 2 - Construction of Roads & Bridges (USD 80 Mn ; INR 480 Crores)
 
S. NoName of the workExecuting AgencyEstimated Cost in Crore INRExpdtt. IncurredStatus/Issues
1Widening up-gradation of Amberpora Haritar Akhoonpora road Baramulla8.375Work in progress - 31% (Physical Progress)
2Construcion of Halmullah Punchpora Kralkut road Sangam Bijbehara district Anantnag4.98Work is in progress - 21 % (Physical Progress)
3Construction of Littter Pulwama road3.36Work is in progress 23 % (Physical Progress)
4Construction of Rohmoo Bridge21.25Work in progress- 42 % (physical progress)
5Construction of Trenz Bridge34.5Work in progress - 30 % (Physical Progress)
6Construction of 1x50 m span trussed Girder steel Girder bridge over Frastharnallah at Waza Mohalla Kreeri at Baramulla7.4Work in progress (Physical progress-32%). Land issue in approach roads and tree cutting
7Construction of 1X50m trussed grider over Niglinallah at Shrakhwara on Putkhah Wagoora Barmulla6.7Work in progress (Physical Progress 47%) -Land Issue in approach roads, canal issue and tree cuttings
8Construction of 1x25.2 m span plate Girder steel lane bridge over nallah sheeshrie on wahdina bandi payeen Baramulla5.32Work in progress- 47% (physical progress)
9Construction of 1x25.20 m RCC double lane bridge over nallah ferozpura Baramulla at trikolbal pattan Baramulla6.31Work in progress - 31% (Physical Progress)
10Construction of 1x19.20 m plate girder double lane steel bridge over niglinallah at ghogidaji Baramulla6.27Physical Progress:46 %. Variation proposal submitted to WB on 19-11-2019.
11Construction of 1x50 span trussed girder double lane steel bridge over ningli nallah a wagila wagoora Baramulla8.66Work in progress 35 % (Physical Progress)
12Construction of steel truss girder bridge 3x 30 m at Asajipora Kamad Sadoora Road km 4th6.31 Finlization of design in progress with PIU. Clearance conveyed by PMU as discussed in WB mission meeting (Feb 17-20). ESIA not submitted.
13Kalaiban Bridge2.63Finalization of design with PIU. Clearance conveyed by PMU as discussed in WB mission meeting in Feb 2020 ESIA not submitted.
14Construction of 2 lane single span 110 m bridge over nallah sindh at Wayil Ganderbal23.79Finalization of design with PIU. Clearance conveyed by PMU as discussed in WB mission meeting in Feb 2020. ESIA not submitted.
15Construction of bridge of Kulgam Chamund road Km-Ist RD-70032.4Finalization of design with PIU. Clearance conveyed by PMU as discussed in WB mission meeting in Feb 2020. ESIA not submitted.
16Construction of 1x45 Mtr trussed girder bridge over nallah Rambiara at Kumar Mohalla Watchi3.11Finalization of design with PIU. Clearance conveyed by PMU as discussed in WB mission meeting in Feb 2020. ESIA not submitted.
4th Tawi Bridge including construction of Protection works ( A1 & A2)0 Dropped
1743M span steel deck bridg over Anji Nallah at Sukhal Ghat,Reasi (complete job)1,22L.O.A issued on 30-07-2019. Contract Agreement signed on 13-03-2020.
18Const. of 165 M (3x55m) span bridge double lane brigde over Betar nallah at village Dhallan18Agreement signed on 07-03-2020.
1958 m span motorable bridge over Katheel Ganjoo to Barsoa over Ghordi nallah and 50 m span motorable bridge from Barso to Pathri over Barmeen nallah Ramnagar Udhampur13.24L.O.A issued on 30-07-2019. Signing of Contract Agreement underway..
20Construction of roads (Kadlabal Lasjan Rambagh Road)-Package-1126Bids recieved on 18-12-2019. Under Evaluation
21Construction of roads (Pampore Pulwama Road)-Package-1
22Construction of roads (Hamaray Sultanpora Nowgam to Sumbul Bridge, Shadipura Khanpeth Sumbal road, Hajin Ajas Via Saidnara )-Package-231.89Awarded A sgreement to be signed.
23Construction of roads (Rigid Pavement of IG Road Rambagh to Civil Secretariat in Srinagar districtPackage-342.52Awarded on 08.01.2020. Agreement yet to be signed.
24Construction of roads ( Rigid Pavement of Eastern Foreshore road, )-Package-3
25Construction of roads (Rigid Pavement of IG Road Peerbagh Bridge to Humhama Chowk in Srinagar)-Package-3
26Construction of roads ( Parimpora Soibugh in Budgam)-Package-3
27Construction of Roads (Sangam Khudwani Road, & Bijbehara waghama via katriteng Road. )-Package-4Awarded. Agreement yet to be signed.
28Construction of Roads ( Sidhra-Surinsar Road (Lot 1)
42.54Awarded. Contract agreement signed on 13-03-2020.
292. Tutan Di Khui to Khada-Madana Road (Lot 2)Tendered on 09.06.2020. Bid submission dated 20.07.2020
30Construction of Roads (Chiralla Link Road and
2. Malaini-Chakrabatti Road)-Package-2
35Tendered on 04.06.2020. Bid submission dated 14.07.2020
31Construction of Roads (Malaini-Chakrabatti Road)-Package-2
32Construction of Roads (Gulati to Shadra Sharief)-Package-338.97LOA issued on 23-12-2019. agreement signed on 13-3-2020.
33Construction of Roads (Anji Panasa Road , Deva Mai Ohli Mandir)-Package-416.04Awarded. Agreement signed on 13-03-2020.