Restoration and strengthening of livelihoods,

The flood resulted in damage to infrastructure and assets such as workshops, stores, tools, raw material, and finished product stocks, which severely impacted non-farm livelihoods in urban centers. In addition to the direct impact on livelihood, the sector is an important contributor to tourism in the region. This component will support:
Subcomponent 4.1 – Restoration of physical and productive assets To finance the restoration of the training workshop and display building within the premises of the main handicraft & handloom market in Srinagar and the School of Design, as well as damaged productive assets in livelihood training institutions and affected craftsman families.
Subcomponent 4.2 –Technical assistance for risk proofing non-farm livelihood To finance: i) vulnerability assessment of non-farm livelihoods and to identify opportunities for increased resilience; and ii) developing options to increase access to finance and insurance for non-farm livelihoods.

Component 4 – Restoration and strengthening of livelihoods: 15 Million USD; 90 Crores

 

Sno.Name of the WorkExecuting AgencyEstimated cost Crore INRExpdtt. incurred in CroresStatus/Issues
1Composite market centre for whole chain silk activity, Govt. Silk Factory Rajbagh.
a). New building and repairs to existing building.I&CD19.14.73Work awarded for Rs 12.5 crore.90% of columns upto F F slab. Shuttering work for slab in progress. (total achieved 37.5%).
b). Consulting services for determining tangible and intangible heritage value.I&CD0.300.30Work completed, Contract is closed.
c). Consulting services for new machinery for silk and wool factories.I&CD0.030.02Work completed, Contract is closed.
d) Procurement of new machinery for Rajbagh silk factoryI&CD4.250Tenders floated, no response received. To be retendered. Retendered Activity created on step.Last date of submission of (re-tendered) work 23-02-2019. Tenders has been put on hold in view of decision taken by PIU to procure the preparatory equipment primarily.
Total23.685.05
2Composite market centre for whole chain wool activity, Govt. Woollen Mills Bemina.
a).New showroom building.I&CD2.050.75Work awarded for 1.5 Crores. In progress. Columns and truss beams completed. Brick work in progress (Total achieved 69.71%).
b).Consulting services for interior design of showroomsI&CD0.490.2690% completed BOQ generated by Consultant only supervision part left
c).Interior works for new showroom.I&CD2.75Work would be advertised by 20.04.2019 proposed w.e.f April 2019.Activity created on step.
d).Procurement of machines for Govt Wool Mills at Bemina, SrinagarI&CD7Out of 4 packages advertised, response received for 1 package only.Technical evaluation completed.Supply order will be issued by 30.04.2019.
Total12.291.01
3E-Commerce portal for Handicrafts and Handlooms
a).Consulting services for development of e-commerce portal.I&CD1.850.00Technical Evaluation completed, no bidder qualified. To be procured through CQS & RFQ. Activity created on the step. cleared by WB. Under process in PIU.
b).Procurement of Digital and IT equipment’s, networking software.I&CD2.750.00Proposed to be taken after consultancy is in place.
Total4.60.00
4Development of comprehensive data base for Artisans of J&K state.
Consultancy services for carrying out Artisan SurveyI&CD2.5Evaluation completed, however one firm which has failed to qualify has filed OWP
5Development of Kashmir Haat & International Trade Centre
a). Civil works for Kashmir HaatI&CD400.00Will be taken up only after feasibility conveyed by consultant.
b).Consultancy services for Kashmir Haat and International Trade Centre.I&CD0.50.00Proposal of shifting Kashmir Haat to Solina Filatures approved by Project Steering Committee.A competition for adaptive reuse of Solina Filatures as Arts, Crafts and Haat to be floated by I&C Department
Total43.000.00
6Development of 3 Handicraft clusters in flood affected areas
a).Buildings for 3 CFC in the craft clustersI&CD3.50.00Will be taken up only after feasibility conveyed by consultancy.
b).Consultancy services for development of Embroidery Cluster at NoorbaghI&CD2.390.077Work in progress monitered by I&CD.
c).Consultancy services for development of PapierMachie Cluster at ZadibalI&CD2.180.145Work in progress, monitered by I&CD.
d).Consultancy services for development of Willow wicker at Ganderbal.I&CD1.930.00Fresh EOI based on the revised qualification criteria as approved by the World Bank floated .The last date of submission of EoI is 18th April 2019.
e).Procurement of machines and equipment for 3 handicraft clusters.I&CD6.000.00Will be taken up only after feasibility conveyed by the consultancy.
Total16.000.222
7Development of 2 handloom clusters in flood affected areas
a).Buildings for 2 CFC in the craft clustersI&CD5.000.00Will be taken up only after feasibility conveyed by consultancy.
b).Consultancy services for development of Wool Cluster at BandiporaI&CD2.50.00Fresh EOI based on the revised qualification criteria as approved by the World Bank floated .The last date of submission of EoI is 18th April 2019.
c).Consultancy services for development of Wool Cluster at PulwamaI&CD2.50.00Fresh EOI based on the revised qualification criteria as approved by the World Bank floated .The last date of submission of EoI is 18th April 2019.
Total100.00
8Brand Building and communication campaign for products of State
a).Consulting services to develop and launch for marketing branding and related promotional campaign for products of state(Kashmir silk wool etc)I&CD10.00EOI opened on 07-01-2019. One bid received. Technical evaluation under process at PIU level.New activity created/approved by WB for re-tendering in view of single tender.Further a fresh EOI issued which was opened on 28.3.2019. Shortlisting under process.
b) Marketing branding and promotional campaign for products of state(Kashmir silk wool etc)I&CD100.00Work will start after submission of road map by the consultant.
Total110.00
9Experiential cum retail and sale centre at Rajbagh Silk Factory
a).Consulting services for design of retail and sale centre at Rajbagh Silk FactoryI&CD0.5Draft TOR submitted to World Bank by PIU.
b) Interior works for retail and sale centreI&CD50.00-do-
Total5.50.00
10Renovation of existing common facility centre for cricket bat manufacturing cluster at Sethar, Anantnag.I&CD4.340.00Revised DPR to be formulated by PIU – I&CD. Issue to declare area as industrial process is going on by PIU – I&CD.CEO JTFRP visited site on 18-01-2019 agreed action with stake holders(as desired submitted).
11Engagement of CDI as a Regional Sector Expert Consultancy for providing regional support towards the implementation of the livelihood component of JTFRPI&CD10.197Work in progress.
12Consulting service for Rajbagh/ Bemina (Civil works)I&CD0.220.05Awarded. Work in progress.
13Training of Artisans in Product Development Cycle for International Market Linkages in Willow Wicker, Paper Mache, Crewel stitch embroidery and Wool in Jammu and KashmirI&CD20Shortllisting completed and will be submitted to World Bank.
14Consultancy for preparation of dossier for inclusion of Srinagar city on UNESCO creative city networkI&CD0.50Work would be awarded by 30.04.2019
15Consultancy for providing technical support for declaring Rajbagh and Solina as UNESCO heritage sitesI&CD0.750The activity has been dropped instead WB has suggested for adaptive re-use of Solina filatures as Art and Crafts centre inclusive of Haat and accordingly clubbed with S.No.5.
Total8.810.247
Grand Total134.836.529