The flood resulted in damage to infrastructure and assets such as workshops, stores, tools, raw material, and finished product stocks, which severely impacted non-farm livelihoods in urban centers. In addition to the direct impact on livelihood, the sector is an important contributor to tourism in the region. This component will support:
Subcomponent 4.1 – Restoration of physical and productive assets To finance the restoration of the training workshop and display building within the premises of the main handicraft & handloom market in Srinagar and the School of Design, as well as damaged productive assets in livelihood training institutions and affected craftsman families.
Subcomponent 4.2 –Technical assistance for risk proofing non-farm livelihood To finance: i) vulnerability assessment of non-farm livelihoods and to identify opportunities for increased resilience; and ii) developing options to increase access to finance and insurance for non-farm livelihoods.
Component 4 – Restoration and strengthening of livelihoods: 15 Million USD; 90 Crores
Sno. | Name of the Work | Executing Agency | Estimated cost Crore INR | Expdtt. incurred in Crores | Status/Issues |
---|---|---|---|---|---|
1 | Composite market centre for whole chain silk activity, Govt. Silk Factory Rajbagh. | ||||
a). New building and repairs to existing building. | I&CD | 19.1 | 4.73 | Work awarded for Rs 12.5 crore.90% of columns upto F F slab. Shuttering work for slab in progress. (total achieved 37.5%). | |
b). Consulting services for determining tangible and intangible heritage value. | I&CD | 0.30 | 0.30 | Work completed, Contract is closed. | |
c). Consulting services for new machinery for silk and wool factories. | I&CD | 0.03 | 0.02 | Work completed, Contract is closed. | |
d) Procurement of new machinery for Rajbagh silk factory | I&CD | 4.25 | 0 | Tenders floated, no response received. To be retendered. Retendered Activity created on step.Last date of submission of (re-tendered) work 23-02-2019. Tenders has been put on hold in view of decision taken by PIU to procure the preparatory equipment primarily. | |
Total | 23.68 | 5.05 | |||
2 | Composite market centre for whole chain wool activity, Govt. Woollen Mills Bemina. | ||||
a).New showroom building. | I&CD | 2.05 | 0.75 | Work awarded for 1.5 Crores. In progress. Columns and truss beams completed. Brick work in progress (Total achieved 69.71%). | |
b).Consulting services for interior design of showrooms | I&CD | 0.49 | 0.26 | 90% completed BOQ generated by Consultant only supervision part left | |
c).Interior works for new showroom. | I&CD | 2.75 | Work would be advertised by 20.04.2019 proposed w.e.f April 2019.Activity created on step. | ||
d).Procurement of machines for Govt Wool Mills at Bemina, Srinagar | I&CD | 7 | Out of 4 packages advertised, response received for 1 package only.Technical evaluation completed.Supply order will be issued by 30.04.2019. | ||
Total | 12.29 | 1.01 | |||
3 | E-Commerce portal for Handicrafts and Handlooms | ||||
a).Consulting services for development of e-commerce portal. | I&CD | 1.85 | 0.00 | Technical Evaluation completed, no bidder qualified. To be procured through CQS & RFQ. Activity created on the step. cleared by WB. Under process in PIU. | |
b).Procurement of Digital and IT equipment’s, networking software. | I&CD | 2.75 | 0.00 | Proposed to be taken after consultancy is in place. | |
Total | 4.6 | 0.00 | |||
4 | Development of comprehensive data base for Artisans of J&K state. | ||||
Consultancy services for carrying out Artisan Survey | I&CD | 2.5 | Evaluation completed, however one firm which has failed to qualify has filed OWP | ||
5 | Development of Kashmir Haat & International Trade Centre | ||||
a). Civil works for Kashmir Haat | I&CD | 40 | 0.00 | Will be taken up only after feasibility conveyed by consultant. | |
b).Consultancy services for Kashmir Haat and International Trade Centre. | I&CD | 0.5 | 0.00 | Proposal of shifting Kashmir Haat to Solina Filatures approved by Project Steering Committee.A competition for adaptive reuse of Solina Filatures as Arts, Crafts and Haat to be floated by I&C Department | |
Total | 43.00 | 0.00 | |||
6 | Development of 3 Handicraft clusters in flood affected areas | ||||
a).Buildings for 3 CFC in the craft clusters | I&CD | 3.5 | 0.00 | Will be taken up only after feasibility conveyed by consultancy. | |
b).Consultancy services for development of Embroidery Cluster at Noorbagh | I&CD | 2.39 | 0.077 | Work in progress monitered by I&CD. | |
c).Consultancy services for development of PapierMachie Cluster at Zadibal | I&CD | 2.18 | 0.145 | Work in progress, monitered by I&CD. | |
d).Consultancy services for development of Willow wicker at Ganderbal. | I&CD | 1.93 | 0.00 | Fresh EOI based on the revised qualification criteria as approved by the World Bank floated .The last date of submission of EoI is 18th April 2019. | |
e).Procurement of machines and equipment for 3 handicraft clusters. | I&CD | 6.00 | 0.00 | Will be taken up only after feasibility conveyed by the consultancy. | |
Total | 16.00 | 0.222 | |||
7 | Development of 2 handloom clusters in flood affected areas | ||||
a).Buildings for 2 CFC in the craft clusters | I&CD | 5.00 | 0.00 | Will be taken up only after feasibility conveyed by consultancy. | |
b).Consultancy services for development of Wool Cluster at Bandipora | I&CD | 2.5 | 0.00 | Fresh EOI based on the revised qualification criteria as approved by the World Bank floated .The last date of submission of EoI is 18th April 2019. | |
c).Consultancy services for development of Wool Cluster at Pulwama | I&CD | 2.5 | 0.00 | Fresh EOI based on the revised qualification criteria as approved by the World Bank floated .The last date of submission of EoI is 18th April 2019. | |
Total | 10 | 0.00 | |||
8 | Brand Building and communication campaign for products of State | ||||
a).Consulting services to develop and launch for marketing branding and related promotional campaign for products of state(Kashmir silk wool etc) | I&CD | 1 | 0.00 | EOI opened on 07-01-2019. One bid received. Technical evaluation under process at PIU level.New activity created/approved by WB for re-tendering in view of single tender.Further a fresh EOI issued which was opened on 28.3.2019. Shortlisting under process. | |
b) Marketing branding and promotional campaign for products of state(Kashmir silk wool etc) | I&CD | 10 | 0.00 | Work will start after submission of road map by the consultant. | |
Total | 11 | 0.00 | |||
9 | Experiential cum retail and sale centre at Rajbagh Silk Factory | ||||
a).Consulting services for design of retail and sale centre at Rajbagh Silk Factory | I&CD | 0.5 | Draft TOR submitted to World Bank by PIU. | ||
b) Interior works for retail and sale centre | I&CD | 5 | 0.00 | -do- | |
Total | 5.5 | 0.00 | |||
10 | Renovation of existing common facility centre for cricket bat manufacturing cluster at Sethar, Anantnag. | I&CD | 4.34 | 0.00 | Revised DPR to be formulated by PIU – I&CD. Issue to declare area as industrial process is going on by PIU – I&CD.CEO JTFRP visited site on 18-01-2019 agreed action with stake holders(as desired submitted). |
11 | Engagement of CDI as a Regional Sector Expert Consultancy for providing regional support towards the implementation of the livelihood component of JTFRP | I&CD | 1 | 0.197 | Work in progress. |
12 | Consulting service for Rajbagh/ Bemina (Civil works) | I&CD | 0.22 | 0.05 | Awarded. Work in progress. |
13 | Training of Artisans in Product Development Cycle for International Market Linkages in Willow Wicker, Paper Mache, Crewel stitch embroidery and Wool in Jammu and Kashmir | I&CD | 2 | 0 | Shortllisting completed and will be submitted to World Bank. |
14 | Consultancy for preparation of dossier for inclusion of Srinagar city on UNESCO creative city network | I&CD | 0.5 | 0 | Work would be awarded by 30.04.2019 |
15 | Consultancy for providing technical support for declaring Rajbagh and Solina as UNESCO heritage sites | I&CD | 0.75 | 0 | The activity has been dropped instead WB has suggested for adaptive re-use of Solina filatures as Art and Crafts centre inclusive of Haat and accordingly clubbed with S.No.5. |
Total | 8.81 | 0.247 | |||
Grand Total | 134.83 | 6.529 |