Corrigendum No 04 for Roads Package Revised/Roads/Kashmir/04

The below referenced Clauses in the Bid Document have been modified and the revised text shall replace the Original text in the Bid Document.

Reference in Bid Document 

Original Criteria

 

Revised Criteria

2.4.2(a) Specific Construction Experience
Joint Venture Where Permitted
All Parties CombinedEach MemberOne Member
Must Meet RequirementMust meet requirement for one contract of 25% valueMust Meet Requirement
Joint Venture Where Permitted
All Parties CombinedEach MemberOne Member
Must Meet RequirementAny one of the Member should meet the requirement.

To download the complete Corrigendum, Click on the Link Below:

Corrigendum 04-Pkg 04