Reconstruction of roads and bridges

The objective of this component is to restore and improve the connectivity disrupted due to the disaster through the reconstruction of damaged roads and bridges. The infrastructure will be designed to withstand earthquake and flood forces as per the latest official design guidelines. The affected areas will benefit by the restored access to markets thereby increasing the economic growth in these areas and timely access to health and education services. Restoration of roads will also serve as supply/rescue lines in the event of a disaster.
The component will finance the reconstruction of damaged roads, bridges and associated drainage and slope stabilization works, retaining walls, breast walls and other structures to increase resilience.

 

Component 2 - Construction of Roads & Bridges (USD 80 Mn ; INR 480 Crores)
 
S. NoName of the workEstimated Cost in Crore INR
1Widening up-gradation of Amberpora Haritar Akhoonpora road Baramulla8.375
2Construcion of Halmullah Punchpora Kralkut road Sangam Bijbehara district Anantnag4.98
3Construction of Littter Pulwama road3.36
4Construction of Rohmoo Bridge21.25
5Construction of Trenz Bridge34.5
6Construction of 1x50 m span trussed Girder steel Girder bridge over Frastharnallah at Waza Mohalla Kreeri at Baramulla7.4
7Construction of 1X50m trussed grider over Niglinallah at Shrakhwara on Putkhah Wagoora Barmulla6.7
8Construction of 1x25.2 m span plate Girder steel lane bridge over nallah sheeshrie on wahdina bandi payeen Baramulla5.32
9Construction of 1x25.20 m RCC double lane bridge over nallah ferozpura Baramulla at trikolbal pattan Baramulla6.31
10Construction of 1x19.20 m plate girder double lane steel bridge over niglinallah at ghogidaji Baramulla6.27
11Construction of 1x50 span trussed girder double lane steel bridge over ningli nallah a wagila wagoora Baramulla8.66
12Construction of steel truss girder bridge 3x 30 m at Asajipora Kamad Sadoora Road km 4th6.31
13Kalaiban Bridge2.63
14Construction of 2 lane single span 110 m bridge over nallah sindh at Wayil Ganderbal23.79
15Construction of bridge of Kulgam Chamund road Km-Ist RD-70032.4
16Construction of 1x45 Mtr trussed girder bridge over nallah Rambiara at Kumar Mohalla Watchi3.11
4th Tawi Bridge including construction of Protection works ( A1 & A2)0
1743M span steel deck bridg over Anji Nallah at Sukhal Ghat,Reasi (complete job)1,22
18Const. of 165 M (3x55m) span bridge double lane brigde over Betar nallah at village Dhallan18
1958 m span motorable bridge over Katheel Ganjoo to Barsoa over Ghordi nallah and 50 m span motorable bridge from Barso to Pathri over Barmeen nallah Ramnagar Udhampur13.24
20Construction of roads (Kadlabal Lasjan Rambagh Road)-Package-1126
21Construction of roads (Pampore Pulwama Road)-Package-1
22Construction of roads (Hamaray Sultanpora Nowgam to Sumbul Bridge, Shadipura Khanpeth Sumbal road, Hajin Ajas Via Saidnara )-Package-231.89
23Construction of roads (Rigid Pavement of IG Road Rambagh to Civil Secretariat in Srinagar districtPackage-342.52
24Construction of roads ( Rigid Pavement of Eastern Foreshore road, )-Package-3
25Construction of roads (Rigid Pavement of IG Road Peerbagh Bridge to Humhama Chowk in Srinagar)-Package-3
26Construction of roads ( Parimpora Soibugh in Budgam)-Package-3
27Construction of Roads (Sangam Khudwani Road, & Bijbehara waghama via katriteng Road. )-Package-4
28Construction of Roads ( Sidhra-Surinsar Road (Lot 1)
42.54
292. Tutan Di Khui to Khada-Madana Road (Lot 2)
30Construction of Roads (Chiralla Link Road and
2. Malaini-Chakrabatti Road)-Package-2
35
31Construction of Roads (Malaini-Chakrabatti Road)-Package-2
32Construction of Roads (Gulati to Shadra Sharief)-Package-338.97
33Construction of Roads (Anji Panasa Road , Deva Mai Ohli Mandir)-Package-416.04